Project Manager
Several noteworthy milestones:
- Completed migration of Wonderware System Platform (version 3.1 to 2017 U3) on-time.
- SCADA system recovery from disaster
- SCADA infrastructure upgrade:
- Physically segregated network to VLAN (including PLC and server network migration)
- Baremetal servers to HCI
- Backup and snapshot strategy
- Physical hardware sizing